ops.office-move·version 1.0.0·draft4 to verify
The company works from the new address on the planned day, the old lease is properly terminated, and every record shows the new address.
The company is moving into an office it has already secured. Not for finding and signing that office — use property.lease-office first; this playbook starts only when the new lease is signed. Not for changing the legal address in the registry alone — that is company.change-legal-address, which this playbook calls at S9. If only the registered address changes (no physical move), run that playbook directly.
Any step can wait until a date and reopens by itself; every closed step leaves evidence (a note, a link, a number).
Write a one-page plan in the tasks module: dates, who moves what, what is not moved (dispose list), budget ceiling.
Done when the plan exists as a task and the owner has been sent it.
Extract: notice period, termination deadline, restoration duties (repainting, cabling removal), deposit.
Done when the last possible termination date is written in the plan as a date, not "per contract".
⛔ "Notice period" from memory or from a template is not a date — only the signed lease counts.
Approval · S3 · owner — the run stops until a named person records the decision
Confirm the move day, the termination date and the budget.
Done when the owner has named the move day and the budget in writing.
Collect at least two mover quotes, book within budget, and reserve the elevator and parking at both buildings.
Done when a written confirmation with price and time slot exists for both addresses.
Order internet at the new address early (installation lead time is often 1–3 weeks), transfer or open the electricity contract, and set the old-address disconnection after the move day.
Done when both providers have confirmed dates in writing.
Label every box with destination zone and contents; keep a numbered box list; back up servers and workstations; photograph cable setups before unplugging.
Done when every box on the floor appears on the list with a zone.
Supervise loading and unloading against the box list; count boxes in and out; photograph any damage at both ends; hand over the old keys per the lease.
Done when the box count matches the list and the keys are handed over with a signed handover note.
Approval · S8 · owner — the run stops until a named person records the decision
Irreversible · S8 — an agent never closes it alone
Send the written termination per the notice period in the lease, agree the inspection date, and sign the handover protocol with the landlord.
Done when the landlord has confirmed the termination and the protocol is signed by both sides.
Approval · S9 · owner — the run stops until a named person records the decision
Run company.change-legal-address for the registry filing (LV: Enterprise Register — the filing itself is approved inside that playbook). Then work a checklist: invoice templates, website footer, Google Business Profile (via growth.google-business-profile), banks, VID (LV), insurers, suppliers, clients, e-mail signatures, and a mail redirect with the postal operator.
Done when every checklist row shows old → new with a date or a screenshot.
⛔ Filing the registry change and notifying the bank are third-party submissions — they wait for the owner's approval in this step. ⚠ verify the current channel and form for reporting a taxpayer address change at vid.gov.lv.
Close the move task (bc tasks add for any follow-ups found late); archive the mover contract, termination, handover protocol, utility confirmations and registry receipt in the documents module; send the owner a three-line summary: moved on, cost vs budget, what still points at the old address.
Done when the move task is closed with follow-up tasks created, the mover contract and confirmations are archived, and the owner has the three-line summary.
| Symptom | Response |
|---|---|
| Internet not live on move day | Escalate to the provider with the written order date; use a mobile hotspot as the documented fallback for the first days; do not rebook movers — connectivity is the constraint, not the truck. |
| Landlord withholds the deposit | Compare the move-in and move-out photo sets; answer in writing within the deadline the lease gives ⚠ verify dispute route and deadline in the lease and, if needed, the Consumer Rights Protection / civil procedure path on likumi.lv. |
| Termination deadline missed | Check the lease for late-termination or renewal clauses immediately; negotiate an early-exit addendum in writing; budget the overlap rent in the next owner review. |
| Registry rejects the address change | Fix the stated reason (usually a document or consent missing), correct and resubmit once; official mail to the old address must be forwarded meanwhile — arrange it the same day. |
| A box or a device is missing | Reconcile against the numbered box list and the last-seen location; check the mover's liability terms from S4 before claiming. |
Mover quotes and contract · termination letter and the landlord's confirmation · signed handover protocol · numbered box list · utility confirmations with dates · registry filing receipt · deposit correspondence · the owner's S3 decision (who, when).
After the move (or every run, if the company moves repeatedly) ask: how many days from decision to the first working day, and which step waited? Did any address-update item surface after S9 — add it to the S9 checklist in the next version? Was the deposit returned in full, and if not, was the move-in photo set the thing that decided it? A new version changes the step that caused the wait or the miss, and says so in its change note.
Obligātās sīkdatnes tur sarunu kopā. Analītika ir izslēgta, līdz tu atļauj — tā neliek nevienu sīkdatni un neglabā ierīces identifikatoru.Necessary storage keeps your conversation together. Analytics is off until you allow it — it sets no cookie and stores no device identifier. Ko mēs glabājamWhat we store